CORE CONCRETE

CoreConcrete founder's professional track record

Professional Track Record

A decade building the evidence

Every figure behind CoreConcrete's methodology is backed by a real, delivered, occupied project. Hover over any project to see the details — and watch the six most recent ones come to life as they looked mid-construction.

The projects shown reflect the founder's hands-on experience as a direct employee of Constructora Colpatria, Suprema Constructora, and other Colombian firms — not work delivered by CoreConcrete, and implying no current affiliation with the companies named. Photographs were taken by the founder himself and, in some cases, sourced from the respective construction companies' own public websites.

Buildings 7, 8 & 9 — Buenos Aires Residential Complex — completed Buildings 7, 8 & 9 — Buenos Aires Residential Complex — under construction

Buildings 7, 8 & 9 — Buenos Aires Residential Complex

Constructora Suprema

Buildings 7, 8 & 9 — Buenos Aires Residential Complex

Site Resident Engineer · 2022 – 2023

105 units$1.3M
Building 3 — Caracas Avenida Residential Complex — completed Building 3 — Caracas Avenida Residential Complex — under construction

Building 3 — Caracas Avenida Residential Complex

Constructora Suprema

Building 3 — Caracas Avenida Residential Complex

Site Resident Engineer · 2020 – 2022

288 units$3.5M
Building 2 — Torres de San Rafael — completed Building 2 — Torres de San Rafael — under construction

Building 2 — Torres de San Rafael

Constructora Colpatria

Building 2 — Torres de San Rafael

Site Resident Engineer · 2018

191 units$2.7M
Paseo de Santa Catalina — completed Paseo de Santa Catalina — under construction

Paseo de Santa Catalina

Constructora Colpatria

Paseo de Santa Catalina

Post-Delivery Masonry Attention · 2017 – 2018

21,528 ft² masonry$500K
Buildings 2 & 3 — Imperial Reservado 2 — completed Buildings 2 & 3 — Imperial Reservado 2 — under construction

Buildings 2 & 3 — Imperial Reservado 2

Constructora Colpatria

Buildings 2 & 3 — Imperial Reservado 2

Finishes Inspector · 2016 – 2017

160 units$5.1M
Bosques de San Patricio — completed Bosques de San Patricio — under construction

Bosques de San Patricio

Constructora Colpatria

Bosques de San Patricio

Site Resident Engineer · 2015 – 2016

264 units$3.39M
Arboleda de Santa Clara 2

Arboleda de Santa Clara 2

Constructora Colpatria

Structure Resident Engineer · 2013 – 2015

384 units$4.75M
Portal de San Basilio

Portal de San Basilio

Constructora Colpatria

Structure Resident Engineer · 2012 – 2013

288 units$3.89M
Quintas de Santa Rita

Quintas de Santa Rita

Constructora Colpatria

Structure Engineer · 2009 – 2012

975 units$11.3M

Hover over any project to view employer, role, dates, and key metrics.